Construction of Sheikh Hasina Textile College, Melandah, Jamalpur.
List of Construction work’s for Sheikh Hasina Textile College, Melandah, Jamalpur are given below –
# Construction of Academic cum Administrative Building
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | NOA- 23.01.901.056.06.055.01.20.03.17/1650, Date: 20 March 2017 |
Commencement Date | 03 Apr 2017 |
Completion Date | 02 Apr 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Dyeing Shed
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | NOA- 23.01.901.056.06.055.01.20.03.17/1653, Date: 20 March 2017 |
Commencement Date | 03 Apr 2017 |
Completion Date | 02 Dec 2017 |
Time Extension | 1) 30 Jul 2018 2) 30 Dec 2018 |
# Constructiong of Weaving Shed
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | NOA- 23.01.901.056.06.055.01.20.03.17/1652, Date: 20 March 2017 |
Commencement Date | 03 Apr 2017 |
Completion Date | 02 Apr 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Spinning Shed
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | NOA- 23.01.901.056.06.055.01.20.03.17/1651, Date: 20 March 2017 |
Commencement Date | 03 Apr 2017 |
Completion Date | 02 Apr 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Boys hostel (100 Bedded) (4 Storied Building with 6 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Jun 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Female hostel (200 Bedded) (4 Storied Building with 6 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Jun 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Office Dormitory (4 Storied Building with 6 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Mar 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Workshop cum library
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | NOA- 23.01.901.056.06.055.01.20.03.17/1654, Date: 20 March 2017 |
Commencement Date | 03 Apr 2017 |
Completion Date | 02 Oct 2017 |
Time Extension | 1) 30 May 2018 2) 30 Dec 2018 |
# Construction of Officers Quarter (4 Storied Building with 6 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Mar 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Principal Quarter (2 Storey Building with 2 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Mar 2018 |
Time Extension | 30-Dec-2018 |
# Construction of Staff Dormitory (4 Storied Building with 6 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Feb 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Staff Quarter (4 Storied Building with 6 storied foundation)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Feb 2018 |
Time Extension | 30 Dec 2018 |
# Construction of Sub-Station building (Single Storied)
Main Procurement Entity | E in C’s Branch |
Work Order/ NOA No. | WORK ORDER NO. 01 DT. 21-06-2017 |
Commencement Date | 21 Jun 2017 |
Completion Date | 20 Dec 2017 |
Time Extension | 30 Dec 2018 |