24. Construction of Sheikh Hasina Textile College, Melandah, Jamalpur.

List of Construction work’s for Sheikh Hasina Textile College, Melandah, Jamalpur are given below –

# Construction of Academic cum Administrative Building

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. NOA- 23.01.901.056.06.055.01.20.03.17/1650, Date: 20 March 2017
Main Contract/Work Value Tk. 8,32,32,900.40
Commencement Date 03 Apr 2017
Completion Date 02 Apr 2018
Time Extension 30 Dec 2018

# Construction of Dyeing Shed

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. NOA- 23.01.901.056.06.055.01.20.03.17/1653, Date: 20 March 2017
Main Contract/Work Value Tk. 3,55,26,476.09
Commencement Date 03 Apr 2017
Completion Date 02 Dec 2017
Time Extension 1) 30 Jul 2018
2) 30 Dec 2018

# Constructiong of Weaving Shed

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. NOA- 23.01.901.056.06.055.01.20.03.17/1652, Date: 20 March 2017
Main Contract/Work Value Tk. 7,22,78,364.26
Commencement Date 03 Apr 2017
Completion Date 02 Apr 2018
Time Extension 30 Dec 2018

# Construction of Spinning Shed

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. NOA- 23.01.901.056.06.055.01.20.03.17/1651, Date: 20 March 2017
Main Contract/Work Value Tk. 8,62,22,952.65
Commencement Date 03 Apr 2017
Completion Date 02 Apr 2018
Time Extension 30 Dec 2018

# Construction of Boys hostel (100 Bedded) (4 Storied Building with 6 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 8,29,04,497.44
Commencement Date 21 Jun 2017
Completion Date 20 Jun 2018
Time Extension 30 Dec 2018

# Construction of Female hostel (200 Bedded) (4 Storied Building with 6 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 9,11,15,951.80
Commencement Date 21 Jun 2017
Completion Date 20 Jun 2018
Time Extension 30 Dec 2018

# Construction of Office Dormitory (4 Storied Building with 6 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 5,68,60,862.10
Commencement Date 21 Jun 2017
Completion Date 20 Mar 2018
Time Extension 30 Dec 2018

# Construction of Workshop cum library

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. NOA- 23.01.901.056.06.055.01.20.03.17/1654, Date: 20 March 2017
Main Contract/Work Value Tk. 2,84,01,964.57
Commencement Date 03 Apr 2017
Completion Date 02 Oct 2017
Time Extension 1) 30 May 2018
2) 30 Dec 2018

# Construction of Officers Quarter (4 Storied Building with 6 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 5,70,27,478.62
Commencement Date 21 Jun 2017
Completion Date 20 Mar 2018
Time Extension 30 Dec 2018

# Construction of Principal Quarter (2 Storey Building with 2 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 1,45,60,327.38
Commencement Date 21 Jun 2017
Completion Date 20 Mar 2018
Time Extension 30-Dec-2018

# Construction of Staff Dormitory (4 Storied Building with 6 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 5,04,67,958.69
Commencement Date 21 Jun 2017
Completion Date 20 Feb 2018
Time Extension 30 Dec 2018

# Construction of Staff Quarter (4 Storied Building with 6 storied foundation)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 4,75,98,433.06
Commencement Date 21 Jun 2017
Completion Date 20 Feb 2018
Time Extension 30 Dec 2018

# Construction of Sub-Station building (Single Storied)

Main Procurement Entity E in C’s Branch
Work Order/ NOA No. WORK ORDER NO. 01 DT. 21-06-2017
Main Contract/Work Value Tk. 18,66,377.66
Commencement Date 21 Jun 2017
Completion Date 20 Dec 2017
Time Extension 30 Dec 2018