06. Slope Protection and River Bank Protective Work at Tajumuddin Upazilla sadar
Slope Protection and River Bank Protective Work at Tajumuddin Upazilla sadar along the Meghna River from Km. 56.350 to Km. 56.950 = 0.600 Km in Polder 56/57. during the year 2016-2017.
Main Procurement Entity | Bangladesh Water Development Board |
Work Order/ NOA No. | NOA No- W-1/169, Dated : 23 July 2017 |
Main Contract/Work Value | Tk. 112,03,07,228.15 |
Commencement Date | 23 Jul 17 |
Completion Date | 3 Feb 19 |