15. Bank Protection work at Kurnibari in Upazila Sariakandi District Bogra.

Bank Protection work at Kurnibari and adjacent areas (from BRE Km. 124.900 to 130.800 = 5900.00m) on the right bank of the Jamuna river in Upazila Sariakandi District Bogra during the FY 2015-2018 under the project “Construction of Retired Embankment including Protection of Right Bank of the Jamuna River from Kurnibari to Chandanbaisha at Sariakandi Upazila in Bogra District.

Main Procurement Entity Bangladesh Water Development Board (BWDB)
Work Order/ NOA No. NOA- W-31/3310, Date: 29 March 2016
Main Contract/Work Value Tk. 2,631,883,359.06
Commencement Date 17 Apr 2016
Completion Date 20 Jun 2018